Field investigations on interaction between jacking pipes and closure of pipe roofs in soft ground
HE Jun-zuo1, LIAO Shao-ming1, CHEN Li-sheng2, CHENG Chi-hao1
1. Department of Underground Architecture and Engineering, Tongji University, Shanghai 200092, China; 2. Shanghai Urban Construction Municipal Group Co., Ltd., Shanghai 200020, China
Abstract:The pipe roofs play a key role in protecting the passing objects in underground crossing projects. In order to construct a strictly closed pipe roof, high jacking precision of each pipe is required. However, the jacking interaction of various adjacent pipes is extremely complicated, which brings uncertainty to the attitude change of each pipe jacking and the final closure error of the pipe roof. This study relies on a certain project crossing a middle ring line by the large-scale ‘pipe roof-box culvert’ method and uses the real-time monitoring approach to record the attitude and deformation of each steel pipe during the jacking process of the pipe roof. Based on the measured data, the interaction of various pipes in the process of jacking as well as the attitude and deformation of the closed pipe roof is analyzed. The results show that: (1) The interaction between the pipes is reflected by the constraint and guiding effects of the previous pipe jacking (anterior pipe) on the attitude of the rear jacking pipe (posterior pipe), and the relative deviation is generally controlled within 4 cm. (2) Affected by the longitudinal stiffness of the steel pipe, the attitude correction of 70% pipes lags behind the machine head which results in relatively large accumulative deviation at the previous stage, but with the decrease of the longitudinal stiffness, the attitude of the pipe changes sharply at the receiving terminal under hard correcting. (3) The attitude of closed pipe roof is well maintained at the originating terminal and the reinforced zone. An obvious change occurs in the middle section, and some pipes even have a large distance among them. Finally, at the receiving terminal, the deviation of most pipes is relatively reduced.
何君佐, 廖少明, 陈立生, 程池浩. 软土地层管幕群顶进的相互作用及闭合姿态的实测分析[J]. 岩土工程学报, 2020, 42(2): 279-288.
HE Jun-zuo, LIAO Shao-ming, CHEN Li-sheng, CHENG Chi-hao. Field investigations on interaction between jacking pipes and closure of pipe roofs in soft ground. Chinese J. Geot. Eng., 2020, 42(2): 279-288.
[1] 陈立生, 程池浩, 葛金科, 等. 管幕箱涵法隧道在软土地层中的应用技术研究[J]. 中国市政工程, 2016(增刊1): 12-15. (CHEN Li-sheng, CHENG Chi-hao, GE Jin-ke, et al.Study on application technology of pipe roof-box culvert method tunnel in soft soil stratum[J]. China Munical Engineering, 2016(S1): 12-15. (in Chinese)) [2] LIAO S M, CHENG C H, CHEN L S.The planning and construction of a large underpass crossing urban expressway in Shanghai: an exemplary solution to the traffic congestions at dead end roads[J]. Tunnelling and Underground Space Technology, 2018, 81: 367-381. [3] 魏纲. 顶管工程土与结构的性状及理论研究[D]. 杭州:浙江大学, 2005. (WEI Gang.Theoretical Study on Properties of Soil and Structure During Pipe Jacking Construction[D]. Hangzhou: Zhejiang University, 2005. (in Chinese)) [4] BAE G J, SHIN H S, SICILIA C, et al.Homogenization framework for three-dimensional elastoplastic finite element analysis of a grouted pipe-roofing reinforcement method for tunneling[J]. International Journal for Numerical and Analytical Methods in Geomechanics, 2005, 29(1): 1-24. [5] SHI Y F, FU J Y, YANG J S, et al.Performance evaluation of long pipe roof for tunneling below existing highway based on field tests and numerical analysis: case study. international[J]. Journal of Geomechanics ASCE, 2017(9): 1-12. [6] 杨仙, 张可能, 李钟, 等. 管幕预筑法中钢管顶进对地面沉降的影响[J]. 沈阳工业大学学报, 2012(4): 469-473. (YANG Xian, ZHANG Ke-neng, LI Zhong, et al.Influence of steel pipe jacking on earth surface settlement in pipe roof pre-construction method[J]. Journal of Shenyang University of Technology, 2012(4): 469-473. (in Chinese)) [7] YANG X, LI Y S.Research of surface settlement for a single arch long-span subway station using the pipe-roof pre-construction method[J]. Tunnelling and Underground Space Technology, 2018, 72: 210-217. [8] 杨仙. 管幕预筑法中密排大直径钢管群顶进研究[D]. 长沙: 中南大学, 2012. (YANG Xian.Research of Large Diameter Jacking-Pipes with Small Space in Pipe-Roof Pre-Construction Method[D]. Changsha: Central South University, 2012. (in Chinese)) [9] 孙钧, 虞兴福, 孙旻, 等. 超大型“管幕-箱涵”顶进施工土体变形的分析与预测[J]. 岩土力学, 2006, 27(7): 1021-1027. (SUN Jun, YU Xing-fu, SUN Min, et al.Analysis and prediction on soft ground deformation of a super-large shallow buried “pipe-roofing and box-culvert” jacking project under construction[J]. Rock and Soil Mechanics, 2006, 27(7): 1021-1027. (in Chinese)) [10] 苏荣军, 陈立生. 软土地层浅覆土下钢管幕顶进沉降分析[J]. 隧道建设, 2018, 38(7): 1236-1242. (SU Rong-jun, CHEN Li-sheng.Settlement analysis of steel piep roof jacking in ultra-shallow covered soft ground[J]. Tunnel Construction, 2018, 38(7): 1236-1242. (in Chinese)) [11] 冼家驹, 张建龙. 管幕施工引起的地面变形计算方法综述[J]. 土工基础, 2016(6): 672-676. (XIAN Jia-ju, ZHANG Jian-long.Review of methods predicting tunnel excavation induced ground subsidence[J]. Soil Engineering and Foundation, 2016(6): 672-676. (in Chinese)) [12] 中航勘察设计研究院有限公司. 田林路下穿中环线道路新建工程岩土工程勘察报告[R]. 北京: 中航勘察设计研究院有限公司, 2016. (China Aviation Institute of Geotechnical Engineering Co., Ltd. Geotechnical investigation report on the new construction project of Tianlin Road underpassing the Central Line Road[R]. Beijing: China Aviation Institute of Geotechnical engineering Co., Ltd., 2016. (in Chinese)