Construction schemes for large excavations near subway facilities
CHEN Jun-sheng1, 2, LIU Shu-zhuo1, MO Hai-hong1, 2, WANG Yi-zhao1
(1. Department of Civil Engineering,South China University of Technology, Guangzhou 510640, China; 2. State Key Laboratory of Subtropical Building Science, South China University of Technology, Guangzhou 510640, China)
Abstract: A large excavation in Guangzhou is taken as an example. Through the spatial relation between the excavation and subway tunnel, the control factors during its construction are introduced. By discussing their advantages and disadvantages, the feasibility of different excavation sequences is studied. A 3D finite element model is established to evaluate the effect of the excavation on the subway tunnel due to different construction schemes. The results indicate that the construction process the excavation should start from the section far away from the subway tunnel to avoid disturbing the soil surrounding the tunnel. Fort the construction over subway tunnel, the piecewise and block excavation method is favorable for controling the subway tunnel. For the construction at both sides of subway tunnel, the eccentric earth pressure due to unbalance excavation should be considered.
陈俊生, 刘叔灼, 莫海鸿, 王一兆. 紧邻地铁设施大型基坑工程施工方案研究[J]. 岩土工程学报, 2012, 34(suppl): 377-382.
CHEN Jun-sheng, LIU Shu-zhuo, MO Hai-hong, WANG Yi-zhao. Construction schemes for large excavations near subway facilities. Chinese J. Geot. Eng., 2012, 34(suppl): 377-382.
[1] 高广运, 高 盟, 杨成斌, 等. 基坑施工对运营地铁隧道的变形影响及控制研究[J]. 岩土工程学报, 2010, 32(3): 453–459. (GAO Guang-yun, GAO Meng, YANG Cheng-bin, et al. Influence of deep excavation on deformation of operating metro tunnels and countermeasures[J]. Chinese Journal of Geotechnical Engineering, 2010, 32(3): 453–459. (in Chinese))[2] 陈忠汉, 程丽萍. 深基坑工程[M]. 北京: 机械工业出版社, 2001. (CHEN Zhong-han, CHENG Li-ping. Deep excavation engineering[M]. Beijing: China Machine Press, 2001. (in Chinese))[3] 高 盟, 高广运, 冯世进, 等. 基坑开挖引起紧贴运营地铁车站的变形控制研究[J]. 岩土工程学报, 2008, 30(6): 818–823. (GAO Meng, GAO Guang-yun, FENG Shi-jin, et.al. Control of deformation of operating subway station induced by adjacent deep excavation[J]. Chinese Journal of Geotechnical Engineering, 2008, 30(6): 818–823. (in Chinese))[4] 孔祥鹏, 刘国彬, 廖少明. 明珠线二期上海体育馆地铁车站穿越施工对地铁一号线车站的影响[J]. 岩石力学与工程学报, 2004, 23(5): 821–825. (KONG Xiang-peng, LIU Guo-bin, LIAO Shao-ming. Influence fo construction of Shanghai stadium transverse station of pearl line phase II on station of metro Line No.1[J]. Chinese Journal of Rock Mechanics and Engineering, 2004, 23(5): 821–825. (in Chinese))[5] 李志高, 曾 远, 刘国彬. 邻近地铁车站基坑开挖位移传递规律数值模拟[J]. 岩土力学, 2008, 29(1): 3104–3108. (LI Zhi-gao, ZENG Yuan, LIU Guo-bin. Numerical simulation of displacement transfer law of excavation adjacent metro station [J]. Rock and Soil Mechanics, 2008, 29(1): 3104–3108. (in Chinese))[6] 王卫东, 吴江斌, 翁其平. 基坑开挖卸载对地铁区间隧道影响的数值模拟[J]. 岩土力学, 2004, 25(增刊2): 251–255. (WANG Wei-dong, WU Jiang-bin, WENG Qi-ping. Numerical modeling of affection of foundation pit excavation on metro tunnel[J]. Rock and Soil Mechanics, 2004, 25(S2): 251–255. (in Chinese))[7] 谢弘帅. 紧贴运营地铁车站深基坑施工变形控制研究(博士学位论文)[D]. 上海: 同济大学, 2005. (XIE Hong-shuai. Study on displacement control of metro station due to ajacent deep excavation[D]. Shanghai: Tongji University, 2005. (in Chinese))[8] 姚燕明, 孙 巍. 深基坑开挖对共用连续墙的既有车站结构内力影响的空间分析[J]. 岩土工程学报, 2006, 28(增刊): 1411–1414. (YAO Yan-ming, SUN Wei. Spatial calculation analysis on internal forces of the existing metro stations having common walls with a deep pit excavation[J]. Chinese Jounal of Geotechnical Engineering, 2006, 28(S0): 1411–1414. (in Chinese))